PLAN ACTIVITY 2 – 30 November

Date PIC Plan Activity Place
2 Nov Leo, Johan and Winner e-Learning :

  • Make slide training material
  • Dry run
  • Review user guide

Knowledgebase :

  • Review user guide
  • Indah to make slide training
@ Office
3 Nov Winner Create User LDAP for Knowledgebase @CG
Johan Write user guide for v-counter @CG
Leo Set up E-Learning Training material and user list in production server : Dokeos @CG
Immanuel Set up E-Learning Training material and user list in production server : Moodle @CG
4 Nov Leo,Johan,Immanuel, Indah, Asry. Fixing User guide and training material for all @office
Winner Fixing Workflow on Procedure document type @CG
5 Nov Johan Review user guide vcounter @office
Immanuel Train Asry for elearning @office
Leo Train Indah for e-learning @office
Winner Fixing Running Text @CG
6 Nov Leo,Johan,Immanuel, Winner, Indah, Asry. Training e-learning at Dea Tower @ADT
9 Nov Leo Check functionality knowledgebase website @CG
Winner Check  look and feel knowledgebase website @CG
Johan Migrating v-counter to Prod Server. @CG
10 Nov Cross Check Knowledgebase website in production server, check functionality, and look and feel. @CG
11 Nov Leo,Johan,Winner Dry Run knowledgebase website and v-Counter @Office
12 Nov ECM Training and v-Counter  for Customer Service at Dea Tower @ADT
13 Nov Leo Fixing change list of training @Office
Johan Fixing change list of training @Office
Winner Fixing change list of training @Office
16 Nov Leo Fixing change list of training @CG
Johan Fixing change list of training @CG
Winner Fixing change list of training @CG
17 Nov Johan Cleansing data @CG
Winner Cleansing data @CG
Leo Cleansing data @CG
18 Nov Leo,Winner,Johan Migrating data (Content) from  share point to knowledge base website @CG
19 Nov Leo,Winner,Johan Migrating data from  share point to knowledge base website production @CG
20 Nov Leo,Winner,Johan Migrating data from  share point to knowledge base website production @CG
23 Nov Leo,Winner,Johan Migrating data from  share point to knowledge base website production @CG
24 Nov Leo,Winner,Johan Testing knowledge base website(e.g. functionality) @CG
25 Nov Leo,Winner,Johan Testing knowledge base website(e.g. functionality) @CG
26 Nov Leo,Winner,Johan Migrating knowledbase website to development server @CG
27 Nov All Notes : Apabila migrasi belum selesai, dilanjutkan pada tgl 27 Nov 2009
28 Nov Leo,Winner,Johan Migrating knowledbase website to development server @CG
29 Nov Leo,Winner,Johan Migrating knowledbase website to development server @CG
30 Nov All Go Live